New Offices Planned for Darlington
October 2026
The town centre development partnership between Darlington Borough Council and Cityheart is proposing new offices on the former Sports Direct site, south of East Street and behind the library. The project aims to deliver high-quality workspace that will attract businesses and employers looking to locate near the new Government Economic Campus off Brunswick Street.
What's the plan?
The proposals are the first phase of the transformation of this area, creating a new commercial hub which complements the Economic Campus, bringing further investment, jobs and opportunities to the town centre.
The plan also involves the demolition of the Wilko building to the north of East Street, which will be used for car parking on an interim basis until further plans are ready to come forward.
The office development will provide:
- More than 50,000 sq ft of Grade A office space
- A highly sustainable building with BREEAM Excellent accreditation
- Market-leading amenities and specification for occupiers
- High-quality design with attractive brick detailing that reflects the character of the local area and complements the listed library
- New public realm, footways and seating areas that will open up access to the River Skerne and improve connections with the town centre
- Safe and secure internal cycle storage
The former Wilko site forms a later phase of the overall masterplan. Demolishing the building will remove a local eyesore and a source of antisocial behaviour from the town centre. In the interim, the site will become a modern, safe and convenient surface car park with dedicated electric vehicle charging bays and accessible parking bays.
How to get involved
Join us at our consultation and meet the team in person. We look forward to talking you through the proposal and getting your feedback.
Wednesday 21st October, 3pm – 7pm
The Dolphin Centre, Darlington Town Centre
If you aren’t able to make our consultation event in person you can still share your feedback with us here.
The consultation starts on 21st October and will close Friday 6th November 2026 ahead of submitting the planning application this winter.
Target Timeline
-
Consultation
October 2026
-
Planning Submission
December 2026
-
Planning Decision
Spring 2027
-
Construction Starts
Winter 2027
-
Completion
Summer 2029